Petone Station: Major Subway Works
Description
Petone Station subway closed from 18 September until June 2024 for seismic strengthening, drainage works, new lighting and cosmetic upgrades.
Customer Impact
Customers will need to use the overbridge at the northern end of the station to cross between the two platforms. Accessible pedestrian entrances from the carpark and Hutt Road footpaths remain open during the project.
Unfortunately, the construction work is taking longer than we expected as we have discovered problems with the existing concrete structures and the drainage infrastructure that requires additional work.
This project is experiencing significant delays. New expected opening date is July 2024.
Project Timeline
Sep 01 2023
- Jul 30 2024
Phase 1: Site Setup
Sep 1 - Sep 18
Completed
Phase 2: Replace floor, improve drainage, improve ramp gradient
Sep 18 - Feb 29
Completed
Phase 3: Strengthen walls & tunnel
Mar 1 - Jun 30
Delayed
Phase 4: Cosmetic upgrades, lighting, pathway installation
May 1 - Jul 30
Delayed