Petone Station: Major Subway Works
Description
Major seismic upgrade works have been completed and the subway is now open for public use. We still have some minor cosmetic work to carry out over the next few months.
Customer Impact
Customers are required to take care when walking through the subway until all works are completed.
Benefits
The upgrades will make for a safer and more beautiful subway.
Unfortunately, this project has been further delayed until November. We apologise for the continued disruption.
Unfortunately, this project has been further delayed by wet weather and the difficulties to construct additional drainage infrastructure below the tidal water table. We apologise for the continued disruption.
Unfortunately, the construction work is taking longer than we expected as we have discovered problems with the existing concrete structures and the drainage infrastructure that requires additional work.
This project is experiencing significant delays. New expected opening date is July 2024.
Project Timeline
Sep 18 2023
- Nov 30 2024
Phase 1: Site Setup
Sep 1 - Sep 18
Completed
Phase 2: Replace floor, improve drainage, improve ramp gradient
Sep 18 - Feb 29
Completed
Phase 3: Strengthen walls & tunnel
Mar 1 - Aug 30
Completed
Phase 4: Cosmetic upgrades, lighting, pathway installation
Aug 30 - Nov 30
Delayed